The Development and Reform Commission of Hainan Province reported that the
Haikou Meilan International Airport Expansion Project will be 14.659 billion
yuan, in the first half of 2018 the investment was 1.363 billion yuan, and the
project is scheduled to be completed in December 2019.
To date, the construction of the terminal zone project at Meilan Airport is
completed, 62.5% of the road surface of the flight zone has been completed and
41.6% of the road surface has been completed, construction of transport
equipment, bridge construction and pipeline equipment is actively developing.
According to the plan, the expansion project of Meilan Airport will complete the
investment in 2018 in the amount of 3 billion yuan. After the completion of the
Meilan Airport expansion project, the T2 international terminal will reach
45,000 square meters, and international passenger traffic will reach 4.2 million
passengers, which will be one of the first places in China.
Похожие новости от https://hainanwel.com/- Related news:
The Development and Reform Commission of Hainan Province reported that the
Haikou Meilan International Airport Expansion Project will be 14.659 billion
yuan, in the first half of 2018 the investment was 1.363 billion yuan, and the
project is scheduled to be completed in December 2019.
To date, the construction of the terminal zone project at Meilan Airport is
completed, 62.5% of the road surface of the flight zone has been completed and
41.6% of the road surface has been completed, construction of transport
equipment, bridge construction and pipeline equipment is actively developing.
According to the plan, the expansion project of Meilan Airport will complete the
investment in 2018 in the amount of 3 billion yuan. After the completion of the
Meilan Airport expansion project, the T2 international terminal will reach
45,000 square meters, and international passenger traffic will reach 4.2 million
passengers, which will be one of the first places in China.